- After concreting, curing and tensioning of cables, the Main Girders are lowered by the main jacks at the rear Suspension Gallow and on the front Pier Bracket.
- The joints in the middle of the Transverse Beam system are released and the Main Girders are moved transversely into a position where the Transverse Beams can pass the piers.
- The MSS is ready for launching. The launching operation to the next concreting position is to be carried out. The two Main Girders are moved independently to the next span.
- During the launching operation, the Suspension Gallow is moved to its next position.
- The two girders are moved transversely and joined in the middle of the Transverse Beam system.
- The Main Girders are raised to the concreting position by the Main Jacks.
- Adjusting the formwork by means of the screw jacks and the adjustable supports.
- For box girder bridges: After placing the reinforcement and tendons of the bottom slab and webs, the Internal Formwork is moved to its next position.
- When placing of reinforcement and tendons is finished, the MSS is ready for concreting of the next span of the superstructure.
- During the concreting period, the rear pair of Pier Brackets are dismounted, moved to the next front pier and re-installed.
|
 |