Our gantries (LG) can be used for both
balanced cantilever as well as for infill span-by-span erection. Depending
on the project dry joint or wet joint erection is required.
- Featuring segmental bridges with dry or glued joints, using erection
methods like infill-spans and balanced cantilever.
- Special hinged overhead gantries (with up to 6 hinges) have been
supplied to accommodate tight horizontal curvature, down to 100m
radii.
- Side-launching of gantry to accommodate erection of separate parallel
double and triple tracks, as well as bifurcation spans.
- Vertical climbing of gantries to allow access for side shifting to
neighbouring bridges, and to accommodate tight vertical curvature and
steep longfall.
- Fully and partly final post-tensioning carried out while the whole
span is still suspended to the gantry, without need to use special
plunger arrangement at each end.
- "Glue-as-you-go", erecting segments without any or only limited
double handling.
- Balanced cantilever and infill-span erection with same gantry.
- Cranes capable of walking through hinged transitions (also
noses).
- Gantry can lift and adjust whole span in level and line
(vertical
and transverse adjustment)
- Gantry is selflaunching, transports also supports by its own
crane.
- Aux. equipment for erecting pre-cast wings at 2nd stage (
if needed).
|
 |